The Central Electricity Regulatory Commission (CERC) has amended the Deviation Settlement Mechanism and Related Matters Regulations,2024 which shall come into force from December 23rd, 2024.
Regulation 3 Amendments:
New clauses have been added to limit power generation based on connectivity granted. Additional clauses clarify open access power sales for renewable and non-renewable energy sources.
Regulation 8 Amendments:
The charges for injecting infirm power will be zero, except when infirm power is scheduled after a successful trial run. In such cases, deviation charges will apply based on the seller’s type. If the system frequency exceeds 50.05 Hz, charges for deviation on infirm power will be waived.
Disclaimer: The information contained in this Article is intended solely for personal non-commercial use of the user who accepts full responsibility of its use. The information in the article is general in nature and should not be considered to be legal, tax, accounting, consulting or any other professional advice. We make no representation or warranty of any kind, express or implied regarding the accuracy, adequacy, reliability or completeness of any information on our page/article.