Submission of NOCs for Extension of Project Registration

Notification/Circular No.: RERA/Pb./Admn/EG(J)/2025/6462 dated May 7, 2025

Applicable Act/Rule: Real Estate (Regulation and Development) Act, 2016

Applicable Section/Rule: Section 6 and Section 8

Effective Date: 1 July, 2025

Punjab Real Estate Regulatory Authority (RERA Punjab), during its meeting held on December 12, 2024, reviewed the process for extending the registration period of real estate projects under the RERA Act.

From July 1, 2025, promoters applying for an extension of registration under Section 6 or Section 8 of the RERA Act must submit all relevant No Objection Certificates (NOCs) that are listed in their License to Develop Colony or any equivalent approval document. This requirement applies to all real estate projects registered with RERA Punjab. The directive ensures that only those projects with up-to-date and complete statutory permissions are considered for registration extension.

Failure to comply with this requirement may result in rejection of extension applications. All promoters are instructed to adhere strictly to this directive.

Disclaimer: The information contained in this Article is intended solely for personal non-commercial use of the user who accepts full responsibility of its use. The information in the article is general in nature and should not be considered to be legal, tax, accounting, consulting or any other professional advice. We make no representation or warranty of any kind, express or implied regarding the accuracy, adequacy, reliability or completeness of any information on our page/article. 