Extension of Real Estate Project validity - Extension fee fixed – Orders [TN RERA]

Notification/Circular No. – Circular No.TNRERA/A2/2761/2025-2 dated August 04, 2025

Applicable Act/Rule: Real Estate (Regulation and Development) Act, 2016

Tamil Nadu Real Estate Regulatory Authority (TNRERA) has issued revised guidelines for extension of real estate project validity and the applicable extension fees, partially modifying the earlier circular (No.TNRERA/A2/4406/2024 dated 11.12.2024).

Extension & Fee Structure:

Type of Extension

Maximum Period

Extension Fee

Conditions

Section 6 – Force majeure

1 year

10% of initial registration fee

Based on force majeure clause

Section 7(3) – 1st extension (no Section 6 given)

1 year

20% of initial registration fee

Subject to TNRERA terms & conditions

Section 7(3) – 2nd & subsequent extensions

6 months at a time

20% of initial registration fee per extension

Based on merit, TNRERA may allow >6 months in special cases

Notes:

  1. If Section 6 extension is already granted, any further Section 7(3) extension is limited to 6 months at a time.
  2. TNRERA may grant more than 6 months extension in special cases in the interest of project completion and allottees.
  3. Authority may revoke or allow continuation of registration subject to further conditions in the interest of allottees/home buyers.

Disclaimer: The information contained in this Article is intended solely for personal non-commercial use of the user who accepts full responsibility of its use. The information in the article is general in nature and should not be considered to be legal, tax, accounting, consulting or any other professional advice. We make no representation or warranty of any kind, express or implied regarding the accuracy, adequacy, reliability or completeness of any information on our page/article. 

To stay updated Subscribe to our newsletter today

Explore other Legal updates on the 1-Comply and follow us on LinkedIn to stay updated 

Post Views: 211

Schedule A Demo