Notification/Circular No. – F.1(167) RJ/RERA/Auth.Meet./2019/1166 dated July 31, 2025
Applicable Act/Rule: Real Estate (Regulation and Development) Act, 2016 & Rajasthan Real Estate (Regulation and Development) Rules, 2017.
To address practical challenges faced by promoters in filing Quarterly Progress Reports (QPRs) and to rationalise delay charges, Rajasthan RERA has issued a revised framework, superseding the earlier order dated February 24, 2025.
Revised Delay Processing Charges for QPR Submission:
Illustration:
No Need for Interim QPR Submissions:
If the promoter misses submission across multiple quarters, they are only required to submit the latest QPR, and not all missed ones. However, delay charges for each missed quarter will still apply.
Strict Action on Non-Compliance:
Pre-condition for Approvals (CC/OC/Mortgage-Free Letter):
Special Provision for Completed Projects:
One-Time Relaxation till October 31, 2025:
Disclaimer: The information contained in this Article is intended solely for personal non-commercial use of the user who accepts full responsibility of its use. The information in the article is general in nature and should not be considered to be legal, tax, accounting, consulting or any other professional advice. We make no representation or warranty of any kind, express or implied regarding the accuracy, adequacy, reliability or completeness of any information on our page/article.